Here's where we're at. . .
- Foundation was formed in early August
- Radiant floor tubing and plumbing was installed and the foundation was poured while we were on vacation August 10 - 20. Septic also installed.
- Slab "cured" for 3 weeks to prepare for grinding. Well system and electric trenching and piping happened during this time.
- First week of September my brother chad and his crew (I helped a bit) ground and then polished the downstairs floor to 80% completion. Downstairs polished concrete floors are going to be distinct and amazing. Couldn't have happened without Chad.
- Windows and doors were ordered this week from Atascadero Glass. Roger Grant has been amazing.
- Framing started on Tuesday. First floor walls went up today. Breathtaking! General Contractor Kevin Hunstad has been a joy throughout. Open, flexible, creative and budget concious.